Vegetation Clearance Works
Vistry plans to begin vegetation clearance from Monday 15th September.
The clearance is expected to take 3–4 days, followed by trial trenching shortly afterwards.
Trial trenching will start in the evening due to road space requirement. All works are expected to take up to 1.5 weeks.
Archaeology works will commence on the 29th September.